NWT Energy Corporation (03) Ltd. - G18X005-G18L8-001

​NWT
Energy Corporation (03) Ltd. has submitted to the Gwich’in Land and Water Board
applications for a Type “A” Land Use Permit for the purpose of constructing, operating and maintaining a wind
turbine, an all season access road, powerlines, and associated electricity
infrastructure at Highpoint, approximately 12 km east of the Town of Inuvik,
NT, and Type “B” Water Licence for water use during project construction.  The applicant requests a term of 5 years for
each authorization, with activities beginning in early 2019.

Documents

Displaying 1 - 1 of 1
Uploaded On or After
Uploaded On or Before
2. Initial/Renewal Application
Preliminary Screening
Document Received/Sent Uploaded
G18X005 G18L8-001 - Inuvik Wind Project - Preliminary Screening Report - Nov16_20.pdf (1.74 MB) November 16, 2020 November 16, 2020