Northwest Territories Power Corporation - MV2022I0013
Status:
Issued
Authorization:
Land Use Permit
Activity:
Powerlines
Start:
November 8, 2022
Expiry:
November 7, 2027
Staff:
Andrew Wheeler
Taltson Hydroelectric Facility Transmission Line - Brushing and maintenance of the existing right of way for the transmission lines from the Taltson Hydroelectric Facility to Pine Point, Fort Resolution, and Fort Smith. Use of equipment. Drilling to identify the main cause(s) of anchor degradation along the Transmission Line.
Displaying 1 - 23 of 23
1. Permit - Licence - Other Issuances
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson - Issuance - Type A Land Use Permit - Nov8_22.pdf (954.93 KB) |
2. Initial/Renewal Application
Document | Received/Sent | Uploaded |
---|---|---|
NTPC – Taltson - Notification - Preliminary Screening Determination - Oct28_22.pdf (500.95 KB) |
5. Reports and Studies
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson - Inspection Report - January 11, 2023 - Jan27_23.pdf (1.58 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson - Phase 2 Notification - Borehole Locations - Jan11_23.pdf (3.25 MB) | ||
NTPC - Taltson - Phase 1 Notification - Anchor Excavation Locations - Jan11_23.pdf (2.51 MB) | ||
NTPC - Taltson - Start Up Notification - Dec9_22.pdf (243.92 KB) |